2206 - Glenview State School - Openbare Project Locatie
-
24th maart 2025, Water off in Building @ 11am
Good morning ladies and gents,
Water will be off for plumbing inspections at 11am for 40 mins.
Thanks,
Evansbuilt, Comino -
28th september 2023, Scaffold Exclusion Zones
Scaffold being dropped around the perimeter of the building - be aware of men working above - stay outside of the exclusion zones.
There will be scaffold stacked up around site.
DO NOT WORK ON ANY SCAFFOLDING - only licensed scaffolders on scaffold
David Wallace - temp Site Manager 0435360093
Huidige weersomstandigheden op locatie
Laatst bijgewerkt om: 21:21
Temperatuur: 21C (App 23C)
Windsnelheid: 4KM/U
Max. Wind: 9KM/U @12:21
Regen sinds 9:00 uur: 0,0mm
Min.temp: 15C @05:46
Max.temp: 28C @15:22
Windvlaag: 4KM/U
Max. windvlaag: 11KM/U @12:21
Waarneming Locatie - Nambour, QUEENSLAND
Tijdzone - Oost-Australische standaardtijd
Weerbericht - vrijdag, 17 april
Partly cloudy.
Min.: 17C Max.: 29C
Kans op neerslag: 20%
Weerbericht locatie - Nambour, QUEENSLAND
Tijdzone - Oost-Australische standaardtijd
Morgen - zaterdag, 18 april
Partly cloudy.
Min.: 17C Max.: 27C
Kans op neerslag: 30%
Verwachte regen: 0 tot 1mm
Weet u wat de PBM-vereisten voor deze locatie zijn?
Zorg dat u voor uw eerste dag op de locatie de juiste veiligheidsapparatuur hebt.
Begin sneller te werken zodra u op de locatie aankomt.
Voltooi uw locatieregistratie eenvoudig online en bespaar zo kostbare tijd.
Weet u wat de PBM-vereisten voor deze locatie zijn?
Zorg dat u voor uw eerste dag op de locatie de juiste veiligheidsapparatuur hebt.
Begin sneller te werken zodra u op de locatie aankomt.
Voltooi uw locatieregistratie eenvoudig online en bespaar zo kostbare tijd.